Verano 8

Verano 8 Scope

  • 1,050 beds in studios, 2-bedroom/1-bathroom and 4-bedroom/2-bathroom apartments
  • Parking garage with space for 853 vehicles
  • Community Center
  • Building Maintenance & Operations facility

Verano 8 West Elevation & Credits

Verano 8 Project Goals & Vision

  • Affordability
  • Community
  • Universal Design
  • Identity & Brand
  • Privacy
  • Sustainability
  • Building Longevity

Verano 8 Project Goals & Vision

Verano 8 Site Map

Verano 8 Building Amenities

  • Entrance lobby with spaces to relax and study
  • Outdoor gathering spaces
  • Study spaces on each floor
  • Barbecues

Verano 8 Community Wide Amenities

  • Dog park
  • Half-court basketball
  • Community garden
  • Volleyball court
  • LEED and FitWel Certified

Verano 8 Community Center Amenities

Community Center amenities will be open to all Graduate and Family Housing residents and will include:

  • Individual and group study space
  • Private event space available for reservation
  • Music practice rooms
  • Wellness Center

Verano 8 Project Schedule

Verano 8 Project Schedule

Verano 8 Project Updates

Expected Work Hours (7 a.m. - 5 p.m.).

Updates for...Project
11/7/2020 – 11/14/2020
  • Grading and excavating foundations on Saturday 11/7. This will result in added noise from the excavating machinery and vehicles
  • Hauling dirt off site Tuesday 11/10 – Friday 11/13.
  • Concrete Placements on Tuesday 11/10, Thursday 11/12 and Friday 11/13; each day will bring about 45 trucks of concrete. You will begin to see vertical columns. This is the next steps to the concrete footings which took place this week.
  • Most of the crews will be off on Wednesday 11/11, in observance of Veteran’s Day.

Verano 8 Open Fall 2022

Verano 8 Questions